Lessons Learned

Lesson Learned





By: Karina Helle

Report No.

1231

Discipline/Origin

Drilling
Experience Transfer Meeting

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2012/06/06
4932 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Borgland Dolphin


Section N/A. What happened:
DONG handover documentation: The OCG 15 section 8.51 states to pump TSW when pressure testing the production packer annulus. This takes a bit of time as lines from pit room need flushing from previous fluid (base oil).

External Actions

Use normal SW, this is available at the cement unit. The fluid will anyway be bleed back after testing, and is only pumped into HP riser, way above the HXT / completion.